A single storey rear extension is consistently one of the most popular home improvements in the UK, and for good reason: it adds usable floor space, creates the potential for a kitchen-diner that transforms family living, and — in the right location — adds 5–15% to property value. This guide covers the planning rules, design decisions, current build costs, and the full project timeline from first sketch to handover.
Permitted Development: The Rules Explained
For most houses (not flats, listed buildings, or properties in designated areas), a single storey rear extension can be built under permitted development (PD) rights — without the need for a full planning application.
Under Class A of Part 1 of the Town and Country Planning (General Permitted Development) (England) Order 2015 (as amended), the conditions are:
- Maximum depth: 3 metres for a semi-detached or terraced house; 4 metres for a detached house
- Maximum eaves height: must not exceed the existing eaves height of the original dwelling
- Maximum overall height: must not exceed 4 metres for a dual-pitched roof or 3 metres for any other roof type
- Materials: must be of similar appearance to the existing dwelling
- Side elevation glazing: no unobscured glazing on side-facing walls or roof slopes where they face a highway or boundary
These are baseline conditions. You lose PD rights entirely if:
- The property is in an Article 4 Direction area (removing PD rights, typically in conservation areas or certain residential estates)
- The building is listed
- The property is a flat or maisonette
- Previous extensions have already consumed the PD allowance (the permitted development limits apply to the original dwelling, not incrementally)
Always check with the local planning authority (LPA) before assuming PD rights apply. A Lawful Development Certificate (LDC) at £258 provides formal written confirmation that is invaluable for future sale or remortgage.
The Neighbour Consultation Scheme (Prior Approval)
If you want to build deeper than the standard PD limits — up to 6 metres for a semi-detached or terraced house or 8 metres for a detached house — you can apply through the Householder Prior Approval process (Class A.1(f)), also known as the Neighbour Consultation Scheme.
Under this process:
- You notify the LPA and pay a fee of £120
- The LPA notifies adjoining owners and gives them 21 days to raise objections
- If objections are received, the LPA assesses the impact on the amenity of adjoining properties only
- If no objections are raised, Prior Approval is automatically granted after 42 days
Prior Approval is not a full planning permission — it is a narrower check focused solely on the impact on neighbours. It does not assess design quality, materials, or streetscape character.
When You Need Full Planning Permission
You will need a full planning application (fee: £258 in England) if:
- You want to build deeper than 6m/8m
- The property is in a conservation area, Area of Outstanding Natural Beauty (AONB), National Park, or World Heritage Site
- The building is listed (listed building consent is also required)
- Previous extensions have consumed the PD allowance
- The LPA has an Article 4 Direction removing PD rights in your area
Full applications target an 8-week determination period, though complex or contested applications regularly take longer.
Design Considerations
Glazing: Bifolds vs Slide-and-Turn vs Fixed
The rear wall of a single storey extension is typically given over to glazing to maximise light and connection to the garden. The main options:
| Glazing Type | Typical Opening Width | Installed Cost | Pros | Cons |
|---|---|---|---|---|
| Bifold doors | Up to 7m+ | £3,500–£12,000 | Maximum opening; popular aesthetic | Many moving parts; more maintenance |
| Slide-and-turn (e.g. Schüco) | Up to 6m | £4,000–£14,000 | Clean sightlines when fully open | Higher cost per m² |
| Fixed glazing + separate door | Any width | £2,000–£8,000 | Thermally efficient; simple | No full opening |
For roof glazing, a roof lantern or structural glass rooflight dramatically increases natural light in the room. A good-quality aluminium roof lantern (2m × 1m) typically costs £1,500–£3,500 supplied and fitted.
Internal Wall Removal and RSJ Calculations
Most single storey rear extensions involve removing a section of the existing rear wall, which may be load-bearing. A structural engineer must calculate the correct steel beam (RSJ or universal column) size and bearing length before Building Control approval can be issued. This is a legal requirement under Part A (Structure) of the Building Regulations.
A typical structural engineer's calculation package for a single beam costs £300–£600. Budget for this separately from your main contractor quote.
Party Wall Act Considerations
The Party Wall etc. Act 1996 may apply even for a standard rear extension:
- Excavations within 3 metres of a neighbouring building (measured to the nearest part of the structure, not the boundary) to a depth greater than the neighbour's foundations require a Section 6 notice — serve at least 1 month before works
- Work to a shared wall — for example, cutting into a party wall to insert an RSJ or remove a chimney breast — requires a Section 2 Party Structure Notice — serve at least 2 months before works
If your extension is set away from both side boundaries and involves no work to a shared wall, the Act may not apply. If in doubt, consult a party wall surveyor — most will advise on whether notice is required for a fixed fee of £100–£200.
Build Costs 2025
| Specification | Cost per m² | Example: 20m² Extension |
|---|---|---|
| Basic (standard finishes, straightforward structure) | £1,800–£2,200/m² | £36,000–£44,000 |
| Mid-spec (underfloor heating, quality glazing, good kitchen) | £2,200–£2,800/m² | £44,000–£56,000 |
| High-spec (premium glazing, stone flooring, structural steelwork) | £2,800–£3,500/m² | £56,000–£70,000 |
These figures cover the construction of the extension shell including foundations, walls, roof structure, glazing, first and second fix trades, plastering, and decoration. They exclude:
- Planning or Prior Approval fees (£120–£258)
- Structural engineer's calculations (£300–£600)
- Building Regulations application (£206–£1,500+ depending on LPA)
- Party wall surveyor fees (£700–£4,000+ if applicable)
- Kitchen or bathroom fit-out beyond standard
- VAT at 20% on all works
Always include a 10–15% contingency for unforeseen groundworks, structural issues, and variations.
Adding Value: What to Expect
A well-designed single storey rear extension typically adds 5–15% to property value, depending on location, quality of execution, and how the existing layout is improved. The return is highest where:
- The existing ground floor layout is genuinely transformed — for example, moving the kitchen into the extension and opening the original kitchen space into a through-room
- The extension is light-filled and integrates the interior with the garden
- The property is in a high-demand area where additional square metres command a meaningful price premium
In lower-value or rural areas, build cost may approach or exceed the value added. Commission a pre-project appraisal from a local RICS-registered valuer before committing to a specification.
Typical Project Timeline
| Stage | Duration |
|---|---|
| Design and initial specification | 3–6 weeks |
| Planning or Prior Approval | 6–10 weeks |
| Party wall notice period (if applicable, can run concurrently) | 4–8 weeks |
| Tender and contractor appointment | 2–4 weeks |
| Build programme on site | 8–14 weeks |
| Snagging and final Building Control sign-off | 1–2 weeks |
| Total: design to handover | 3–6 months |
A single storey rear extension is one of the most straightforward and value-accretive home improvements available to UK homeowners — but get the planning rules right before commissioning drawings, appoint a structural engineer before any walls come down, and build in contingency for what's underground.
Further Reading
- Permitted Development Rights UK: Extensions — full Class A PD conditions for extensions, including the cumulative limit and Article 4 exceptions
- Party Wall Agreement UK Guide — when the Party Wall etc. Act 1996 applies to extensions and how to serve notice correctly
- How to Get Planning Permission for a House Extension UK — when full planning is required and how to maximise chances of approval
- Right to Light Disputes: What UK Homeowners Need to Know — why your neighbour may have a private right to light claim even after you receive planning permission
- Building Regulations Approval UK — the full plans vs building notice routes and what Building Control inspects at each stage